Quorum Drive Reconstruction from Dallas North Tollway to DART Rail Right-of-Way

View all

Project

Project Status: 

Engineering Design Phase

Proposition B of the 2019 Bond Program is the reconstruction of Quorum Drive from the Dallas North Tollway to the DART Rail Right-of-Way.  Quorum Drive was originally built in the early to mid-1980s. The scope will include but not be limited to utility upsizing to handle continued growth in Addison, incorporation of the Master Transportation and Trails Master Plans, ADA improvements, and the replacement of traffic signals at three intersections.